Sale Schedule
FALL 2008 BOND SALE SCHEDULE - REVISED OCTOBER 22, 2008
Contact State Dept. of Ed. |
School Building Aid Deadline |
October 03, 2008 |
Deadline for all applications to be returned to the Bond Bank |
| |
|
October 03, 2008 |
Notify Bond Counsels of identity of governmental units and amount and purposes of municipal bonds |
| |
|
October 17, 2008 |
All legal information from participants due at their bond counsel |
| |
|
October 24, 2008 |
Send RFP to underwriter firms
|
| |
|
| November 03, 2008 |
RFPs due from underwriters |
| |
|
| November 05, 2008 |
Set loan rates, select underwriter and mail loan agreements to Bond Counsels |
| |
|
November 06, 2008 |
Bond Counsels mail loan agreements to governmental units and clear debt schedules with the Bond Bank |
| |
|
November 14, 2008 |
Bond Counsels send Preliminary Opinions to rating agencies and the Bond Bank |
| |
|
November 7- November 21, 2008 |
Meeting of the Participant’s Governing Board for the Certificate of Vote Regarding Authorization of Bonds and Approval of Loan Agreements with the NH Municipal Bond Bank |
| |
|
November 21, 2008 |
Loan Agreements returned to Bond Bank |
| |
|
November 24, 2008 |
Preliminary Official Statements mailed |
| |
|
| December 09-10, 2008 |
Sale (Dec 9th) Bond Bank Board Meeting (Dec 10th) |
| |
|
December 11, 2008 |
Bond Counsels mail bonds to governmental units |
| |
|
December 15, 2008 |
Participants return Bonds to Bond Counsel |
| |
|
December 15, 2008 |
Bond Counsels send Bonds to Edwards, Angell, Palmer & Dodge |
| |
|
| December 17-18, 2008 |
Pre-closing and Closing - Bond proceeds wired to participants on December 18, 2008. |
| |
|
December 18, 2008 |
Date of NHMBB Bonds and interest start date |
| |
|
July 15, 2009 |
First interest payment due |
| |
|
January 15, 2010 |
First principal and second interest payment due |
Note: Dates outlined indicate involvement of the city, town, or district participating in the sale.
Sale Schedule
SPRING 2009 BOND SALE SCHEDULE - TENTATIVE
Contact State Agency |
School Building Aid Deadline |
 |
 |
April 17, 2009 |
Deadline for all applications to be returned to the Bond Bank |
April 17, 2009
|
Notify Bond Counsels of identity of governmental units and amount and purposes of municipal bonds |
April 24, 2009 |
All legal information from participants due at their bond counsel |
May 7, 2009 |
Set loan rates and mail loan agreements to Bond Counsels |
May 11, 2009
|
Bond Counsels mail loan agreements to governmental units and clear debt schedules with the Bond Bank |
May 15, 2009 |
Bond Counsels send Preliminary Opinions to rating agencies and the Bond Bank |
May 11-May 29, 2009
|
Meeting of the Participant’s Governing Board for the Certificate of Vote Regarding Authorization of Bonds and Approval of Loan Agreements with the NH Municipal Bond Bank |
 |
 |
May 29, 2009 |
Loan Agreements returned to Bond Bank |
June 2, 2009
June 10-11, 2009 |
Preliminary Official Statements mailed
Sale (June 10th) Bond Bank Board Meeting (June 11th) |
June 12, 2009 |
Bond Counsels mail bonds to governmental units |
June 26, 2009 |
Participants return Bonds to Bond Counsel |
June 29, 2009 |
Bond Counsels send Bonds to Edwards Angell Palmer & Dodge |
July 15-16, 2009 |
Pre-closing and Closing - Bond proceeds wired to participants on
July 16, 2009.
July 16, 2009 - Interest start date for municipality's Bond. |
July 1, 2009 |
Date of Bonds and interest start date |
February 15, 2010
August 15, 2010 |
First interest payment due
First principal and second interest payment due |
|
|
Note: Dates outlined indicate involvement of the city, town, or district participating in the sale.
|